November 2026 Update
As of November 18, 2026, the City has:
- Replaced more than 100 service lines in the Phase 4 project area.
- Removed and replaced more than 5,000 feet of lead or lead-impacted service line pipe in the Phase 4 project area.
- Removed and replaced more than 480 service lines and more than 24,000 feet of lead-impacted service line pipe through the overall program.
The City is also nearing completion of its service line verification work. By early 2027, crews expect to inspect more than 1,000 service lines through a process called potholing. Potholing involves carefully digging small test holes so crews can visually identify the underground pipe material and confirm City records.
This work supports safe, reliable drinking water and helps Greeley prepare for upcoming federal Lead and Copper Rule Improvements requirements.
Share November 2026 Update on Facebook
Share November 2026 Update on X (formerly Twitter)
Share November 2026 Update on Linkedin
Email November 2026 Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends