Our crews continue to make strong progress on the south side of 16th Street. Sidewalk and curb demolition between 8th and 11th Avenues is now complete, and pavement and utility work are well underway. To keep the project on schedule, crews will be working on Saturdays.
Work Complete
Travel is only open to westbound traffic on 16th Street; traffic signals have been removed or bagged, and the intersections are now partial roundabouts
Sidewalk and curb & gutter demolition on the south side of 16th Street is complete from 8th to 11th Avenue
Work Ongoing
Subgrade removal and compaction between 8th and 11th Avenue
Underground drainage piping and manholes are being installed at 16th Street & 9th Avenue
Sidewalk paving from 10th to 11th Avenue
Upcoming Work
Concrete pavement pours between 8th and 9th Avenues
Curb and gutter from 9th to 10th Avenue
Construction on the south side of 16th Street is now 14% complete.