Construction Update
Progress continues as crews made major headway on concrete paving and drainage improvements. With significant drainage structures in place and pavement progressing block by block, the corridor is increasingly taking shape. Crews will continue working on Saturdays to keep the project moving forward.
Work Complete
The street is open to westbound traffic on 16th Street. Traffic signals have been removed, and the intersections are now partial roundabouts.
Trench drain installation between 9th and 11th Avenue
Underground drainage piping and manhole installation at 16th Street and 9th Avenue
Concrete pavement pours at the 9th Avenue roundabout and 16th Street
Concrete pavement pours between 10th and 11th Avenue
Work Ongoing
Curb and gutter placement from 9th to 10th Avenue
Sidewalk pours from 9th to 10th Avenue
Concrete pavement pours between 9th and 10th Avenue
Upcoming Work
Concrete seat wall and masonry wall construction
Curb and gutter pours at 16th Street and 10th Avenue roundabout
Concrete pavement pours at 16th Street and 10th Avenue roundabout
The work on the south side of 16th Street is now 40% complete.