Here’s your weekly construction update for the 16th Street Corridor project:

Work Completed

  • 16th Street Eastbound remains closed, with all-way stops at each intersection.

  • Sidewalk and curb/gutter pours are complete between 10th and 11th Avenues.

  • Concrete roadway paving has also been completed between 10th and 11th Avenues.

Work Ongoing

  • Sidewalk and curb/gutter removal and replacement continue on the north side of 16th Street between 9th and 10th Avenues.

  • Concrete pavement pours are in progress between 8th and 9th Avenues.

Work Upcoming

  • Installation of underground irrigation, as well as culverts and drainpipes

  • Continued concrete pavement pours between 9th and 10th Avenues

Project Timeline

  • Work on the north side of 16th Street is on schedule for completion by the end of August 2025.

  • Construction will then shift to the south side, with work wrapping up in Fall 2025.

  • Final landscaping and public art installations will follow in Spring 2026, when weather and conditions allow.