16th Street Construction Update (updated 8/4)
Here’s your weekly update on the 16th Street Enhancement project. Thank you for your continued patience as we move forward with improvements that will enhance accessibility and long-term infrastructure for the area.
Work Completed or Ongoing
Westbound travel remains closed on 16th Street between 8th and 11th Avenues. All intersections are now all-way stops.
Concrete pavement pouring is in process between 8th and 9th Avenues.
Tree removal is complete on the UNC campus (south side of 16th Street)
Upcoming Work
Sidewalk and curb/gutter demolition will begin this week between 9th and 10th Avenues, working in half-block increments to help maintain customer access to nearby businesses.
Continued pouring of curb, gutter, and sidewalk concrete throughout the corridor.
Ongoing installation of underground irrigation.
The project is now 15% complete.
Project Timeline
Work on the north side of 16th Street is on schedule for completion by the end of August 2025.
Construction will then shift to the south side, with work wrapping up in Fall 2025.
Final landscaping and public art installations will follow in Spring 2026, when weather and conditions allow.