16th Street Enhancement Project (updated 9/15)

Crews are making steady progress on the south side of 16th Street. This stage includes sidewalk, curb and pavement replacement as well as utility upgrades. Thank you for your continued patience and support as we work to improve this vital corridor.

Work Completed

  • Travel is now open to westbound traffic on 16th Street. Traffic signals have been removed or bagged, and the intersections are now partial roundabouts

  • Remaining light poles have been removed on the south side of 16th Street

  • Sidewalk and curb & gutter demolition on the southern half of 16th Street is complete from 8th to 9th Avenue

Work Ongoing

  • Sidewalk and curb & gutter demolition on the south side of 16th Street is underway beginning at 9th Avenue and heading west towards 11th Avenue

Upcoming Work

  • Current streetlights to be removed. Temporary streetlights will be installed to ensure public safety within the work zone.

  • Underground electrical and irrigation installation from 8th to 9th Avenues

  • Curb & gutter work from 8th to 9th Avenue

Project Timeline

  • Work on the north side of the street is completed.

  • Construction is now shifted to the south side of the street, with 5% of this phase now complete.

  • Final landscaping and public art installations will occur in Spring 2026, once weather and planting conditions allow.