16th Street Update Early March 2026

Early March 2026 Update


The 16th Street Corridor Enhancement Project continues to progress steadily with Phase 2 holding at 75% completion. With both eastbound and westbound traffic open on 16th Street, crews are focused on finishing surface features such as brick pavers and striping, along with vertical elements including seat walls and light poles. Work activities continue to be carefully sequenced to balance winter weather constraints while keeping the project aligned with the overall construction schedule.


Important Notice:

Eastbound and westbound lanes of 16th Street will be closed for one day each, on separate days, for light pole installation. Roadway closures will be announced in advance as soon as delivery dates are confirmed. Please plan accordingly and watch for notifications.


Recent Accomplishments

  • 16th Street is fully open to both eastbound and westbound traffic
  • Topsoil and soil stabilizer installation completed throughout the project
  • Trash receptacle installation completed
  • Asphalt patching completed
  • Sculpture foundations completed
  • Bench installation completed


Current Work in Progress

  • Brick paver installation around concrete seat walls
  • Concrete seat wall and masonry wall construction
  • Drainage installation at masonry wall
  • Sign installation


Coming Soon

  • Light pole installation (requires brief lane closures)
  • Bus shelter installation
  • Sculpture installation


16th Street Alley Project

Excellent progress continues on the complementary alley project. The box culvert over Ditch #3 is now complete, and work is continuing on the south parking lot. Recent work includes:

  1. Box culvert over Ditch #3 (completed)
  2. North alley apron paving (completed)
  3. Rip rap installation (completed)
  4. South parking lot work (in progress)


Once the south parking lot paving is finished, this project will provide additional convenient parking for residents and downtown visitors.


Looking Ahead

Some elements of Phase 1, including landscaping, lighting, and art installations, will be completed as part of Phase 2 when weather permits in the spring. The project remains on schedule and within authorized funding. The project team continues to work diligently to complete the enhancement work while minimizing impacts to the community.


Thank you for your continued patience and support as we work to complete this important enhancement project for the Greeley community.


Project Contacts

Justin Johnson, Construction Superintendent

303.947.0184 | jjohnson@wadsco.com


Roch Labossiere, City of Greeley

970.617.8514 | roch.labossiere@greeleygov.com