16th Street Update Mid-February

Mid-February 2026 Update

The 16th Street Corridor Enhancement Project continues to progress steadily, with Phase 2 holding at 75% completion. With both eastbound and westbound traffic open on 16th Street, crews are focused on finishing surface features, such as brick pavers and striping, as well as vertical elements, including seat walls and light poles. Work activities are being carefully sequenced to balance winter weather constraints while keeping the project aligned with the overall construction schedule.


Current Status:

Good news! The access on 10th Avenue (southern access) has reopened. Both 9th and 10th Avenues are now fully accessible to residents and visitors.

Recent Accomplishments

  • 16th Street is fully open to both eastbound and westbound traffic
  • Topsoil and soil stabilizer installation completed throughout the project
  • Trash receptacle installation completed
  • Asphalt patching completed
  • Concrete seat walls poured

Current Work in Progress

  • Paver installation
  • Masonry wall construction
  • Sign installation

Coming Soon

· Light pole and Wiring Installation

· Bus Shelter Installation

· Sculpture Foundations


16th Street Alley Project

A complementary project is underway to enhance parking and access along the 16th Street corridor. Significant progress has been made with the box culvert over Ditch #3 successfully poured and crews now working on backfill, compaction, and grouted rip rap. Work includes:

  • Construction of a cast-in-place culvert over Ditch #3 (completed)
  • North alley concrete paving
  • South alley asphalt work
  • Paving of the alleyway and south parking lots

Once complete, this project will open additional parking spaces for residents and patrons along the 16th Street corridor.

Looking Ahead

Some elements of Phase 1, including landscaping, lighting, and art installations, will be completed as part of Phase 2 when weather permits in the spring. The project team continues to work diligently to complete the enhancement work while minimizing impacts on the community.

Thank you for your continued patience and support as we work to complete this important enhancement project for the Greeley community.

Project Contacts

Justin Johnson, Construction Superintendent

303.947.0184 | jjohnson@wadsco.com

Roch Labossiere, City of Greeley

970.617.8514

Share 16th Street Update Mid-February on Facebook Share 16th Street Update Mid-February on Twitter Share 16th Street Update Mid-February on Linkedin Email 16th Street Update Mid-February link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>