16th Street Early April Update
Phase 2 of the 16th Street Corridor Enhancement Project is now 85% complete! Work is progressing well, with crews focused on the remaining vertical elements, plantings, and irrigation. 16th Street remains open in both directions.
⚠ Upcoming Lane Closures — Please Plan Ahead
Temporary lane closures are coming to 16th Street over the next two weeks:
Next Week — Permanent Striping Installation
- Eastbound lanes closed: Monday & Tuesday
- Westbound lanes closed: Wednesday & Thursday
The Following Week — Light Pole Installation
- One-day closures in each direction (specific dates to be announced)
We appreciate your patience during these brief closures as we put the finishing touches on this project!
What's Been Completed
- 16th Street open in both directions
- Paver installation
- Bus shelter installation
- Sculpture foundations
- Trash receptacles
- Asphalt patching
- Topsoil and ground cover installation throughout the corridor
Work Currently Underway
- Seat wall and masonry wall construction
- Signage installation
- Plantings and irrigation
Coming Up Next
- Permanent striping (next week)
- Light pole installation (week of [DATE])
- Sculpture installation
16th Street Alley — Now Complete!
The 16th Street Alley is fully open. Improvements include new concrete pavement, a culvert over Ditch #3, fencing, and a repaved south parking lot — adding convenient parking for residents and businesses along the corridor.
Project Status at a Glance
Phase 2 Progress |
~85% complete |
Budget |
Within authorized funding |
16th Street |
Open in both directions |
9th & 10th Avenues |
Open |
Note: Some Phase 1 landscaping, lighting, and art installations will be completed during Phase 2 as weather allows.
Thank you to all who made this project possible. We hope you will take an opportunity to visit 16th Street and enjoy the businesses and improvements along this corridor.