What to Expect through September 4, 2026
Construction activities will continue on and near 14th Avenue, 14th Avenue Court, and 13th Avenue.
- Residents along 14th Avenue can expect to hear from a contractor soon about relocating their private service connection.
- Crews will install meter pits on 14th Avenue Court.
- Water main installation will continue on 14th Avenue Court.
- Saw-cutting and other preparation work will take place on 13th Avenue.
Traffic Impacts
- No-parking signs will be installed on 13th Avenue as work approaches the area.
- Motorists should use caution when driving on 14th Avenue and 14th Avenue Court while construction activities continue.
Share What to Expect through September 4, 2026 on Facebook
Share What to Expect through September 4, 2026 on X (formerly Twitter)
Share What to Expect through September 4, 2026 on Linkedin
Email What to Expect through September 4, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends