Share What to Expect: August 10-14, 2026 on Facebook
Share What to Expect: August 10-14, 2026 on X (formerly Twitter)
Share What to Expect: August 10-14, 2026 on Linkedin
Email What to Expect: August 10-14, 2026 link
Crews will continue work on the Farr Neighborhood waterline relocation project during the upcoming week, with water main installation continuing along 14th Avenue Court. Residents can expect trenching, pipe installation, and crews working in the area as this portion of the project moves forward. Meter pit installation is also planned along 14th Avenue.
Concrete pan installation is expected to take place on the northern side of 25th Street. Traffic control on 25th Street should begin coming down as the week progresses, though traffic patterns may change while work is underway. Travelers should use caution, follow posted signage, and allow extra time when moving through the area.
Crews will continue work on the Farr Neighborhood waterline relocation project during the upcoming week, with water main installation continuing along 14th Avenue Court. Residents can expect trenching, pipe installation, and crews working in the area as this portion of the project moves forward. Meter pit installation is also planned along 14th Avenue.
Concrete pan installation is expected to take place on the northern side of 25th Street. Traffic control on 25th Street should begin coming down as the week progresses, though traffic patterns may change while work is underway. Travelers should use caution, follow posted signage, and allow extra time when moving through the area.
Share What to Expect: July 27-31, 2026 on Facebook
Share What to Expect: July 27-31, 2026 on X (formerly Twitter)
Share What to Expect: July 27-31, 2026 on Linkedin
Email What to Expect: July 27-31, 2026 link
Crews will continue work on the Farr Neighborhood waterline relocation project during the week of July 27-31, with pipe installation planned in 14th Avenue Court. Residents can expect saw-cutting, trenching, and crews working in the area as this portion of the project moves forward. Parking impacts are anticipated on 14th Avenue Court while work is underway.
Paving activities on 25th Street are expected to continue, and the street will begin to reopen as paving is completed. Traffic control patterns may change as work progresses, so travelers should use caution, follow posted signage, and allow extra time when moving through the area.
Crews will continue work on the Farr Neighborhood waterline relocation project during the week of July 27-31, with pipe installation planned in 14th Avenue Court. Residents can expect saw-cutting, trenching, and crews working in the area as this portion of the project moves forward. Parking impacts are anticipated on 14th Avenue Court while work is underway.
Paving activities on 25th Street are expected to continue, and the street will begin to reopen as paving is completed. Traffic control patterns may change as work progresses, so travelers should use caution, follow posted signage, and allow extra time when moving through the area.
Share What to Expect: July 20-24, 2026 on Facebook
Share What to Expect: July 20-24, 2026 on X (formerly Twitter)
Share What to Expect: July 20-24, 2026 on Linkedin
Email What to Expect: July 20-24, 2026 link

Crews will continue work on the Farr Neighborhood waterline relocation project near the top of the 14th Avenue horseshoe, focusing on connection points to the University of Northern Colorado. Properties east and west of the horseshoe (see graphic) may experience temporary water shutdowns, and notices will be distributed to the affected homes.
Additional work includes tying in 14th Avenue to 25th Street and continuing paving activities on 25th Street. Traffic control patterns may change as paving progresses, so travelers should use caution and follow posted signage in the area.

Crews will continue work on the Farr Neighborhood waterline relocation project near the top of the 14th Avenue horseshoe, focusing on connection points to the University of Northern Colorado. Properties east and west of the horseshoe (see graphic) may experience temporary water shutdowns, and notices will be distributed to the affected homes.
Additional work includes tying in 14th Avenue to 25th Street and continuing paving activities on 25th Street. Traffic control patterns may change as paving progresses, so travelers should use caution and follow posted signage in the area.
Share Reporting Property Damage on Facebook
Share Reporting Property Damage on X (formerly Twitter)
Share Reporting Property Damage on Linkedin
Email Reporting Property Damage link
If you believe construction activity caused damage to your property, please report it to the City as soon as soon as you can. Prompt reporting is important because it allows City staff and the contractor to inspect the issue, document conditions, and determine next steps. If repairs are made before the damage is reported and reviewed, it may limit the City’s or contractor’s ability to verify the claim.
If you notice possible damage:
- Report it right away
- Take photos, if possible
- Avoid making permanent repairs before the issue is reviewed, unless there is an immediate safety concern
Please note that repair or reimbursement requests may be denied if the City and contractor were not given the opportunity to inspect the reported damage before repairs were completed.
If you believe construction activity caused damage to your property, please report it to the City as soon as soon as you can. Prompt reporting is important because it allows City staff and the contractor to inspect the issue, document conditions, and determine next steps. If repairs are made before the damage is reported and reviewed, it may limit the City’s or contractor’s ability to verify the claim.
If you notice possible damage:
- Report it right away
- Take photos, if possible
- Avoid making permanent repairs before the issue is reviewed, unless there is an immediate safety concern
Please note that repair or reimbursement requests may be denied if the City and contractor were not given the opportunity to inspect the reported damage before repairs were completed.
Share What to Expect: July 6-10, 2026 on Facebook
Share What to Expect: July 6-10, 2026 on X (formerly Twitter)
Share What to Expect: July 6-10, 2026 on Linkedin
Email What to Expect: July 6-10, 2026 link

Project Activities for This Week
Impact on Traffic
Traffic control is expected to shift often throughout the week as crews complete paving activities.

Project Activities for This Week
Impact on Traffic
Traffic control is expected to shift often throughout the week as crews complete paving activities.