Farr Neighborhood Water Line Relocation Project
Many of the existing water lines in the Farr Neighborhood are nearly 70 years old and are in backyards. Because these older lines are more likely to leak or break, repairs can require crews to dig through yards and disturb fences, landscaping and private property.
To improve service and make future maintenance easier, the city is moving water lines to the front of homes and installing new water meters there. Each home will be connected to the new system, and the old backyard water lines will be taken out of service. Sewer lines will remain in place and will not be moved.
Where Work Will Occur
Work will begin west of 11th Avenue between 24th and 25th Streets and continue west toward 17th Avenue.
Project Schedule
Phase 1A began in January 2026, with construction of a new water main and water meter pits on 12th Avenue Court. Once that work was complete in May 2026, an outside contractor connected each property to its new water meter pit.

Future work includes:
Phase 1A: Completed (May 2026)
Phase 1B: Beginning summer 2026
Phase 1C: Beginning fall 2026
Phase 1D: Following completion of Phase 1C
Why This Project Matters
- Improves long-term water service reliability
- Reduces the need for emergency repairs
- Makes future maintenance faster and less disruptive
- Improves fire protection for homes in the neighborhood
What Residents Can Expect
- Temporary road closures and water shutoffs for residents along 25th Street between 10th and 17th Avenues
- Single-lane traffic and limited street parking in active work zones
- Possible unplanned water outages, which are expected to last only a few hours
- Driveway parking available on weekdays between 5 p.m. and 8 a.m. and all day on weekends
The city will notify affected residents in advance of any planned water shutoffs and will work to maintain access to homes during construction whenever possible.
Staying Informed
Because traffic control may change as construction moves through the neighborhood, residents are encouraged to check this project page regularly for updates on schedules, access and construction impacts.
Many of the existing water lines in the Farr Neighborhood are nearly 70 years old and are in backyards. Because these older lines are more likely to leak or break, repairs can require crews to dig through yards and disturb fences, landscaping and private property.
To improve service and make future maintenance easier, the city is moving water lines to the front of homes and installing new water meters there. Each home will be connected to the new system, and the old backyard water lines will be taken out of service. Sewer lines will remain in place and will not be moved.
Where Work Will Occur
Work will begin west of 11th Avenue between 24th and 25th Streets and continue west toward 17th Avenue.
Project Schedule
Phase 1A began in January 2026, with construction of a new water main and water meter pits on 12th Avenue Court. Once that work was complete in May 2026, an outside contractor connected each property to its new water meter pit.

Future work includes:
Phase 1A: Completed (May 2026)
Phase 1B: Beginning summer 2026
Phase 1C: Beginning fall 2026
Phase 1D: Following completion of Phase 1C
Why This Project Matters
- Improves long-term water service reliability
- Reduces the need for emergency repairs
- Makes future maintenance faster and less disruptive
- Improves fire protection for homes in the neighborhood
What Residents Can Expect
- Temporary road closures and water shutoffs for residents along 25th Street between 10th and 17th Avenues
- Single-lane traffic and limited street parking in active work zones
- Possible unplanned water outages, which are expected to last only a few hours
- Driveway parking available on weekdays between 5 p.m. and 8 a.m. and all day on weekends
The city will notify affected residents in advance of any planned water shutoffs and will work to maintain access to homes during construction whenever possible.
Staying Informed
Because traffic control may change as construction moves through the neighborhood, residents are encouraged to check this project page regularly for updates on schedules, access and construction impacts.
-
Farr Neighborhood Public Meeting Recap
Share Farr Neighborhood Public Meeting Recap on Facebook Share Farr Neighborhood Public Meeting Recap on X (formerly Twitter) Share Farr Neighborhood Public Meeting Recap on Linkedin Email Farr Neighborhood Public Meeting Recap link
Approximately 30 Farr Neighborhood residents attended a public meeting at Jackson Elementary School on Thursday, November 12, to learn about upcoming phases of the City’s water main relocation project.Phase 1 began in January 2026 west of 11th Avenue and north of 25th Street, with construction continuing west to 17th Avenue. The public meeting focused on residents living south of 25th Street, where Phases 2 through 4 are planned from 2027 through 2029.
Residents arrived with a variety of questions, and project staff were happy to provide answers and additional information. Attendees received clarification on water service line connections, potential landscape impacts and the project’s anticipated timeline. 

Approximately 30 Farr Neighborhood residents attended a public meeting at Jackson Elementary School on Thursday, November 12, to learn about upcoming phases of the City’s water main relocation project.Phase 1 began in January 2026 west of 11th Avenue and north of 25th Street, with construction continuing west to 17th Avenue. The public meeting focused on residents living south of 25th Street, where Phases 2 through 4 are planned from 2027 through 2029.
Residents arrived with a variety of questions, and project staff were happy to provide answers and additional information. Attendees received clarification on water service line connections, potential landscape impacts and the project’s anticipated timeline. 

-
What to Expect through November 27
Share What to Expect through November 27 on Facebook Share What to Expect through November 27 on X (formerly Twitter) Share What to Expect through November 27 on Linkedin Email What to Expect through November 27 link
Construction activities will continue on 13th Avenue.• Residents on 13th Avenue can expect private service line installations throughout the week.
• Installations of water mains on 25th Street continue
Traffic Impacts
• Motorists should use caution when traveling along streets while construction activities are underway.
Construction activities will continue on 13th Avenue.• Residents on 13th Avenue can expect private service line installations throughout the week.
• Installations of water mains on 25th Street continue
Traffic Impacts
• Motorists should use caution when traveling along streets while construction activities are underway.
-
Farr Neighborhood Public Meeting Set for Nov. 12
Share Farr Neighborhood Public Meeting Set for Nov. 12 on Facebook Share Farr Neighborhood Public Meeting Set for Nov. 12 on X (formerly Twitter) Share Farr Neighborhood Public Meeting Set for Nov. 12 on Linkedin Email Farr Neighborhood Public Meeting Set for Nov. 12 link
Have questions about the project in your neighborhood?The City of Greeley is planning a water main relocation project to improve the reliability, safety, and long-term maintenance of the water system serving the Farr Neighborhood.
Please join us at the upcoming Neighborhood Public Meeting to learn what the project means for your property, ask questions, and understand the steps ahead.
Neighborhood Public Meeting
- Thursday, November 12, 6-8 p.m.
- Jackson Elementary School, 2002 25th Street, Greeley
Have questions about the project in your neighborhood?The City of Greeley is planning a water main relocation project to improve the reliability, safety, and long-term maintenance of the water system serving the Farr Neighborhood.
Please join us at the upcoming Neighborhood Public Meeting to learn what the project means for your property, ask questions, and understand the steps ahead.
Neighborhood Public Meeting
- Thursday, November 12, 6-8 p.m.
- Jackson Elementary School, 2002 25th Street, Greeley
-
What to Expect through October 23, 2026
Share What to Expect through October 23, 2026 on Facebook Share What to Expect through October 23, 2026 on X (formerly Twitter) Share What to Expect through October 23, 2026 on Linkedin Email What to Expect through October 23, 2026 link
Construction activities will continue on and near 14th Avenue, 14th Avenue Court, and 13th Avenue.- Residents along 14th Avenue and 14th Avenue Court can expect private service line relocations throughout the week.
- City crews will continue installing meter pits and public service lines along 13th Avenue.
- Patching activities will occur along 14th Avene Court.
Traffic Impacts
- Motorists should use caution when traveling on 14th Avenue, 14th Avenue Court, and 13th Avenue while construction activities are underway.
Construction activities will continue on and near 14th Avenue, 14th Avenue Court, and 13th Avenue.- Residents along 14th Avenue and 14th Avenue Court can expect private service line relocations throughout the week.
- City crews will continue installing meter pits and public service lines along 13th Avenue.
- Patching activities will occur along 14th Avene Court.
Traffic Impacts
- Motorists should use caution when traveling on 14th Avenue, 14th Avenue Court, and 13th Avenue while construction activities are underway.
-
What to Expect: August 10-14, 2026
Share What to Expect: August 10-14, 2026 on Facebook Share What to Expect: August 10-14, 2026 on X (formerly Twitter) Share What to Expect: August 10-14, 2026 on Linkedin Email What to Expect: August 10-14, 2026 link
Crews will continue work on the Farr Neighborhood waterline relocation project during the upcoming week, with water main installation continuing along 14th Avenue Court. Residents can expect trenching, pipe installation, and crews working in the area as this portion of the project moves forward. Meter pit installation is also planned along 14th Avenue.Concrete pan installation is expected to take place on the northern side of 25th Street. Traffic control on 25th Street should begin coming down as the week progresses, though traffic patterns may change while work is underway. Travelers should use caution, follow posted signage, and allow extra time when moving through the area.
Crews will continue work on the Farr Neighborhood waterline relocation project during the upcoming week, with water main installation continuing along 14th Avenue Court. Residents can expect trenching, pipe installation, and crews working in the area as this portion of the project moves forward. Meter pit installation is also planned along 14th Avenue.Concrete pan installation is expected to take place on the northern side of 25th Street. Traffic control on 25th Street should begin coming down as the week progresses, though traffic patterns may change while work is underway. Travelers should use caution, follow posted signage, and allow extra time when moving through the area.
-
What to Expect: July 27-31, 2026
Share What to Expect: July 27-31, 2026 on Facebook Share What to Expect: July 27-31, 2026 on X (formerly Twitter) Share What to Expect: July 27-31, 2026 on Linkedin Email What to Expect: July 27-31, 2026 link
Crews will continue work on the Farr Neighborhood waterline relocation project during the week of July 27-31, with pipe installation planned in 14th Avenue Court. Residents can expect saw-cutting, trenching, and crews working in the area as this portion of the project moves forward. Parking impacts are anticipated on 14th Avenue Court while work is underway.Paving activities on 25th Street are expected to continue, and the street will begin to reopen as paving is completed. Traffic control patterns may change as work progresses, so travelers should use caution, follow posted signage, and allow extra time when moving through the area.
Crews will continue work on the Farr Neighborhood waterline relocation project during the week of July 27-31, with pipe installation planned in 14th Avenue Court. Residents can expect saw-cutting, trenching, and crews working in the area as this portion of the project moves forward. Parking impacts are anticipated on 14th Avenue Court while work is underway.Paving activities on 25th Street are expected to continue, and the street will begin to reopen as paving is completed. Traffic control patterns may change as work progresses, so travelers should use caution, follow posted signage, and allow extra time when moving through the area.
-
What to Expect: July 20-24, 2026
Share What to Expect: July 20-24, 2026 on Facebook Share What to Expect: July 20-24, 2026 on X (formerly Twitter) Share What to Expect: July 20-24, 2026 on Linkedin Email What to Expect: July 20-24, 2026 link
Crews will continue work on the Farr Neighborhood waterline relocation project near the top of the 14th Avenue horseshoe, focusing on connection points to the University of Northern Colorado. Properties east and west of the horseshoe (see graphic) may experience temporary water shutdowns, and notices will be distributed to the affected homes.
Additional work includes tying in 14th Avenue to 25th Street and continuing paving activities on 25th Street. Traffic control patterns may change as paving progresses, so travelers should use caution and follow posted signage in the area.

Crews will continue work on the Farr Neighborhood waterline relocation project near the top of the 14th Avenue horseshoe, focusing on connection points to the University of Northern Colorado. Properties east and west of the horseshoe (see graphic) may experience temporary water shutdowns, and notices will be distributed to the affected homes.
Additional work includes tying in 14th Avenue to 25th Street and continuing paving activities on 25th Street. Traffic control patterns may change as paving progresses, so travelers should use caution and follow posted signage in the area.
-
Reporting Property Damage
Share Reporting Property Damage on Facebook Share Reporting Property Damage on X (formerly Twitter) Share Reporting Property Damage on Linkedin Email Reporting Property Damage linkIf you believe construction activity caused damage to your property, please report it to the City as soon as soon as you can. Prompt reporting is important because it allows City staff and the contractor to inspect the issue, document conditions, and determine next steps. If repairs are made before the damage is reported and reviewed, it may limit the City’s or contractor’s ability to verify the claim.
If you notice possible damage:
- Report it right away
- Take photos, if possible
- Avoid making permanent repairs before the issue is reviewed, unless there is an immediate safety concern
Please note that repair or reimbursement requests may be denied if the City and contractor were not given the opportunity to inspect the reported damage before repairs were completed.
If you believe construction activity caused damage to your property, please report it to the City as soon as soon as you can. Prompt reporting is important because it allows City staff and the contractor to inspect the issue, document conditions, and determine next steps. If repairs are made before the damage is reported and reviewed, it may limit the City’s or contractor’s ability to verify the claim.
If you notice possible damage:
- Report it right away
- Take photos, if possible
- Avoid making permanent repairs before the issue is reviewed, unless there is an immediate safety concern
Please note that repair or reimbursement requests may be denied if the City and contractor were not given the opportunity to inspect the reported damage before repairs were completed.
-
What to Expect: July 6-10, 2026
Share What to Expect: July 6-10, 2026 on Facebook Share What to Expect: July 6-10, 2026 on X (formerly Twitter) Share What to Expect: July 6-10, 2026 on Linkedin Email What to Expect: July 6-10, 2026 link
Project Activities for This Week
Water main installation on the north side of the 14th Avenue cul-de-sac
Meter pit staking and installation on 14th Avenue
Paving of westbound lanes on 25th Street
Impact on Traffic
Traffic control is expected to shift often throughout the week as crews complete paving activities.

Project Activities for This Week
Water main installation on the north side of the 14th Avenue cul-de-sac
Meter pit staking and installation on 14th Avenue
Paving of westbound lanes on 25th Street
Impact on Traffic
Traffic control is expected to shift often throughout the week as crews complete paving activities.
-
HM
Phone 970-336-4168 Email WaterMainRelocation@greeleygov.com
-
Phase 1A Completed (May 2026)
Farr Neighborhood Water Line Relocation Project has finished this stage -
Phase 1B: Summer 2026
Farr Neighborhood Water Line Relocation Project is currently at this stage -
Phase 1C: Fall 2026
this is an upcoming stage for Farr Neighborhood Water Line Relocation Project -
Phase 1D: Following completion of Phase 1C
this is an upcoming stage for Farr Neighborhood Water Line Relocation Project
- Why is the City moving the water lines?
- What improvements will this project provide?
- Will my sewer line be moved?
- What is happening on my property?
- How long will the project last?
- Will I lose water service during construction?
- Will roads be closed?
- Will I still be able to access my home?
- Where should I park during construction?
- What if traffic control changes near my home?
- What should I do if I think construction damaged my property?