d News, Greeley! Just in time for the holiday shopping season, 10th Street in downtown Greeley is reopened from 8th to 10th avenues!
The construction team brought in additional crews and worked weekends to reopen this important roadway as quickly and safely as possible.
Other downtown construction updates:
10th Street & 8th Avenue: Intersection reopening, with work continuing south on 8th Avenue.
10th Street & 9th Avenue: Intermittent closures over the next several weeks.
9th Avenue & 12th Street: Intersection closures for stormwater improvements.
North 11th Avenue Railroad Crossing: Closed Nov. 10–13.
Downtown businesses are open! Thank you for your patience as we continue making progress on these important improvements.
Goo
d News, Greeley! Just in time for the holiday shopping season, 10th Street in downtown Greeley is reopened from 8th to 10th avenues!
The construction team brought in additional crews and worked weekends to reopen this important roadway as quickly and safely as possible.
Other downtown construction updates:
10th Street & 8th Avenue: Intersection reopening, with work continuing south on 8th Avenue.
10th Street & 9th Avenue: Intermittent closures over the next several weeks.
9th Avenue & 12th Street: Intersection closures for stormwater improvements.
North 11th Avenue Railroad Crossing: Closed Nov. 10–13.
Downtown businesses are open! Thank you for your patience as we continue making progress on these important improvements.
Share Box Culvert Work Starts on 9th Avenue on Facebook
Share Box Culvert Work Starts on 9th Avenue on X (formerly Twitter)
Share Box Culvert Work Starts on 9th Avenue on Linkedin
Email Box Culvert Work Starts on 9th Avenue link
Crews are now placing rebar forms for the new underground stormwater box culvert at 9th Avenue and 12th Street. The reinforcing steel will strengthen the structure as crews prepare to pour the culvert’s sides, followed later by its ceiling.
The finished culvert will be 5 feet tall and 12 feet wide—about the width of three golf carts parked side by side—and will move more stormwater beneath downtown streets during heavy rainfall to help reduce flood risk.
Because the work area is constrained by the downtown location, crews are constructing the culvert directly inside the excavation rather than installing pre-built sections.
Monthly stormwater utility fees help fund this project and other maintenance and capacity improvements throughout Greeley.
Crews are now placing rebar forms for the new underground stormwater box culvert at 9th Avenue and 12th Street. The reinforcing steel will strengthen the structure as crews prepare to pour the culvert’s sides, followed later by its ceiling.
The finished culvert will be 5 feet tall and 12 feet wide—about the width of three golf carts parked side by side—and will move more stormwater beneath downtown streets during heavy rainfall to help reduce flood risk.
Because the work area is constrained by the downtown location, crews are constructing the culvert directly inside the excavation rather than installing pre-built sections.
Monthly stormwater utility fees help fund this project and other maintenance and capacity improvements throughout Greeley.
Share 8th Avenue Open to Southbound Traffic at 10th Street on Facebook
Share 8th Avenue Open to Southbound Traffic at 10th Street on X (formerly Twitter)
Share 8th Avenue Open to Southbound Traffic at 10th Street on Linkedin
Email 8th Avenue Open to Southbound Traffic at 10th Street link
Good news for Downtown Greeley! Southbound traffic is moving again through the intersection of 8th Avenue and 10th Street! The intersection reopened Tuesday, October 20, marking another milestone in the downtown infrastructure improvements project.
This reopening helps improve access to downtown businesses and makes it easier to travel through the area. Construction continues in other parts of downtown, so please follow posted detours and plan ahead.
Good news for Downtown Greeley! Southbound traffic is moving again through the intersection of 8th Avenue and 10th Street! The intersection reopened Tuesday, October 20, marking another milestone in the downtown infrastructure improvements project.
This reopening helps improve access to downtown businesses and makes it easier to travel through the area. Construction continues in other parts of downtown, so please follow posted detours and plan ahead.
Share Downtown Infrastructure Improvements Open House ~ Event Recap on Facebook
Share Downtown Infrastructure Improvements Open House ~ Event Recap on X (formerly Twitter)
Share Downtown Infrastructure Improvements Open House ~ Event Recap on Linkedin
Email Downtown Infrastructure Improvements Open House ~ Event Recap link



Overview
The City of Greeley and the project team hosted an open house on September 24 to share updates on the Downtown Revitalization Infrastructure Program and the 12th Street Outfall project.
More than 30 residents and business owners joined City representatives and project team members for a brief presentation and an opportunity to ask questions. Attendees came from a range of locations near downtown.
Conversations continued after the presentation, giving community members, City staff and construction teams more time to connect.
Presentation Highlights
The presentation covered the project overview, approach, timeline and ways to contact the project team. Adam Prior, Ryan Davis and Jackie Michaelsen spoke and answered questions.
Attendees also received a flyer in English and Spanish with information on where to find future project updates.
Translation and Accessibility Support
To support inclusive community and industry engagement, bilingual event materials were provided in both English and Spanish.
Onsite Spanish-English interpretation services were available.



Overview
The City of Greeley and the project team hosted an open house on September 24 to share updates on the Downtown Revitalization Infrastructure Program and the 12th Street Outfall project.
More than 30 residents and business owners joined City representatives and project team members for a brief presentation and an opportunity to ask questions. Attendees came from a range of locations near downtown.
Conversations continued after the presentation, giving community members, City staff and construction teams more time to connect.
Presentation Highlights
The presentation covered the project overview, approach, timeline and ways to contact the project team. Adam Prior, Ryan Davis and Jackie Michaelsen spoke and answered questions.
Attendees also received a flyer in English and Spanish with information on where to find future project updates.
Translation and Accessibility Support
To support inclusive community and industry engagement, bilingual event materials were provided in both English and Spanish.
Onsite Spanish-English interpretation services were available.
Share Stormwater Construction Set to Begin on 9th Avenue on Facebook
Share Stormwater Construction Set to Begin on 9th Avenue on X (formerly Twitter)
Share Stormwater Construction Set to Begin on 9th Avenue on Linkedin
Email Stormwater Construction Set to Begin on 9th Avenue link
Do you live or travel near 9th Avenue and 12th Street?
As soon as Monday, September 21, the block of 9th Avenue between 11th and 12th streets will close for several months while crews install new stormwater infrastructure.
Have Concerns?
If you live or regularly travel in the area, we want to hear from you. Let the project team know about regular deliveries, property access needs, scheduled services or other concerns we should be aware of during the closure by emailing InfrastructureComms@thelevel5.com.
What is Being Done?
The work area is tight, and the stormwater structures are too large to install as pre-cast pieces. Instead, crews will build the structures on-site. This construction approach will create more durable structures that provide a long-term solution for downtown infrastructure needs.
Building the system in place will also help reduce project costs. Once complete, the project will help reduce downtown flooding and support future development by improving the City’s water, sewer, and stormwater infrastructure.
For details on other road closures, go to https://greeleyco.gov/news/2026/20260916-street-closures-planned-along-9th-avenue-near-st-peters-catholic-church/
Do you live or travel near 9th Avenue and 12th Street?
As soon as Monday, September 21, the block of 9th Avenue between 11th and 12th streets will close for several months while crews install new stormwater infrastructure.
Have Concerns?
If you live or regularly travel in the area, we want to hear from you. Let the project team know about regular deliveries, property access needs, scheduled services or other concerns we should be aware of during the closure by emailing InfrastructureComms@thelevel5.com.
What is Being Done?
The work area is tight, and the stormwater structures are too large to install as pre-cast pieces. Instead, crews will build the structures on-site. This construction approach will create more durable structures that provide a long-term solution for downtown infrastructure needs.
Building the system in place will also help reduce project costs. Once complete, the project will help reduce downtown flooding and support future development by improving the City’s water, sewer, and stormwater infrastructure.
For details on other road closures, go to https://greeleyco.gov/news/2026/20260916-street-closures-planned-along-9th-avenue-near-st-peters-catholic-church/
Share Open House Set for Sept. 24, 2026 on Facebook
Share Open House Set for Sept. 24, 2026 on X (formerly Twitter)
Share Open House Set for Sept. 24, 2026 on Linkedin
Email Open House Set for Sept. 24, 2026 link
Major infras
tructure improvements are underway, and we want to keep you informed about what’s happening now and what’s coming next. Join the City of Greeley for a Downtown Revitalization Project Open House to learn more about the Downtown Infrastructure Improvements and 12th Street Storm Drain Outfall Project.
📅 Thursday, Sept. 24
⏰ 5:30-7 p.m. | Brief presentation at 6 p.m.
📍 Kimberly’s Event Center, 1029 8th Ave.
Stop by to meet the project team, ask questions and learn about current and upcoming work downtown. The event is free and open to the public. No RSVP is required.
Major infras
tructure improvements are underway, and we want to keep you informed about what’s happening now and what’s coming next. Join the City of Greeley for a Downtown Revitalization Project Open House to learn more about the Downtown Infrastructure Improvements and 12th Street Storm Drain Outfall Project.
📅 Thursday, Sept. 24
⏰ 5:30-7 p.m. | Brief presentation at 6 p.m.
📍 Kimberly’s Event Center, 1029 8th Ave.
Stop by to meet the project team, ask questions and learn about current and upcoming work downtown. The event is free and open to the public. No RSVP is required.
Share Intersection Closure (8th Avenue & 10th Street) Set for September 1 on Facebook
Share Intersection Closure (8th Avenue & 10th Street) Set for September 1 on X (formerly Twitter)
Share Intersection Closure (8th Avenue & 10th Street) Set for September 1 on Linkedin
Email Intersection Closure (8th Avenue & 10th Street) Set for September 1 link
Beginning Tuesday, September 1, the intersection of 8th Avenue and 10th Street will close for several weeks while crews complete water and sewer work. The intersection may reopen at times as work allows, but lane closures may remain in place.
Work will also take place north and south of 10th Street, and traffic routes may change during construction.
Please use posted detours:
- From the south: 13th Street to 11th Avenue
- From the north: 5th Street to 11th Avenue
Businesses, sidewalks, pedestrian access and parking lots will remain open. Some on-street parking near the intersection may be unavailable.
Read the entire news release.
View active detours and parking map.
Beginning Tuesday, September 1, the intersection of 8th Avenue and 10th Street will close for several weeks while crews complete water and sewer work. The intersection may reopen at times as work allows, but lane closures may remain in place.
Work will also take place north and south of 10th Street, and traffic routes may change during construction.
Please use posted detours:
- From the south: 13th Street to 11th Avenue
- From the north: 5th Street to 11th Avenue
Businesses, sidewalks, pedestrian access and parking lots will remain open. Some on-street parking near the intersection may be unavailable.
Read the entire news release.
View active detours and parking map.
Share Missed the Groundbreaking Ceremony? Watch it here! on Facebook
Share Missed the Groundbreaking Ceremony? Watch it here! on X (formerly Twitter)
Share Missed the Groundbreaking Ceremony? Watch it here! on Linkedin
Email Missed the Groundbreaking Ceremony? Watch it here! link
Share Intersection Closure Set for Monday, August 17 on Facebook
Share Intersection Closure Set for Monday, August 17 on X (formerly Twitter)
Share Intersection Closure Set for Monday, August 17 on Linkedin
Email Intersection Closure Set for Monday, August 17 link

Beginning on Monday, August 17, the
intersection of 7th Avenue and 10th Street will fully close while crews install new underground water and sewer lines.
Drivers should follow posted detours using 6th Avenue and 8th Avenue and plan for temporary on-street parking closures nearby. Businesses, sidewalks and pedestrian access will remain open throughout construction.
What to Expect
- Drivers should follow posted detours on 6th Avenue and 8th Avenue.
- Temporary street parking closures will be in place near the intersection on 7th Avenue and 10th Street.
- Businesses, sidewalks, and pedestrian access will remain open during construction.
- Greeley-Evans Transit Route 4 will be affected by the detour. Riders should check route schedules for updates.
You can find project photos, parking information, and detour maps on the Project Dashboard.

Beginning on Monday, August 17, the
intersection of 7th Avenue and 10th Street will fully close while crews install new underground water and sewer lines.
Drivers should follow posted detours using 6th Avenue and 8th Avenue and plan for temporary on-street parking closures nearby. Businesses, sidewalks and pedestrian access will remain open throughout construction.
What to Expect
- Drivers should follow posted detours on 6th Avenue and 8th Avenue.
- Temporary street parking closures will be in place near the intersection on 7th Avenue and 10th Street.
- Businesses, sidewalks, and pedestrian access will remain open during construction.
- Greeley-Evans Transit Route 4 will be affected by the detour. Riders should check route schedules for updates.
You can find project photos, parking information, and detour maps on the Project Dashboard.
Share It's Official! Groundbreaking Ceremony Signals Start of Project on Facebook
Share It's Official! Groundbreaking Ceremony Signals Start of Project on X (formerly Twitter)
Share It's Official! Groundbreaking Ceremony Signals Start of Project on Linkedin
Email It's Official! Groundbreaking Ceremony Signals Start of Project link
City leaders, project partners, downtown businesses and community members gathered Tuesday morning to mark the official start of Greeley’s Downtown Infrastructure Improvements Project, a major milestone in the City’s Downtown Revitalization Program. The multi-year project will replace aging water, sewer and stormwater infrastructure beneath downtown, much of which is more than 100 years old, to reduce flood risk, improve public safety and support future roadway, streetscape and mobility improvements.
“A stronger downtown infrastructure system benefits more than one neighborhood,” said Mayor Pro-Tem Melissa McDonald. “It protects public and private investment, supports local businesses, improves access, and helps ensure downtown remains a safe, active, and welcoming center of our city.”
Construction is underway along 7th Avenue between 9th and 10th streets, the first phase of nearly 20 blocks of planned improvements throughout downtown Greeley.
Read more about the groundbreaking ceremony.




City leaders, project partners, downtown businesses and community members gathered Tuesday morning to mark the official start of Greeley’s Downtown Infrastructure Improvements Project, a major milestone in the City’s Downtown Revitalization Program. The multi-year project will replace aging water, sewer and stormwater infrastructure beneath downtown, much of which is more than 100 years old, to reduce flood risk, improve public safety and support future roadway, streetscape and mobility improvements.
“A stronger downtown infrastructure system benefits more than one neighborhood,” said Mayor Pro-Tem Melissa McDonald. “It protects public and private investment, supports local businesses, improves access, and helps ensure downtown remains a safe, active, and welcoming center of our city.”
Construction is underway along 7th Avenue between 9th and 10th streets, the first phase of nearly 20 blocks of planned improvements throughout downtown Greeley.