The West Greeley Project is an exciting long-term initiative aimed at planning for the future growth and development of Greeley’s western area! This project is all about fostering coordinated development, enhancing infrastructure, and encouraging economic investment within the city’s expanding western growth boundary.

Currently, several vibrant projects are underway on the west side of Greeley, each contributing to the area’s promising transformation:

  • Residential and Mixed-Use Neighborhoods:
    • One of the developments is Cascadia, a privately-owned residential and commercial community brought to life by the Water Valley Company. This project is set to move forward, creating a lively neighborhood for residents and visitors alike.
    • Additionally, we have other residential developments in the works, such as Delantero, Tri Pointe, and Poudre Heights, each poised to add unique living spaces to our community.Strategic Planning in Motion: The Vision for West Greeley Map
  • Community Infrastructure and Utilities: A key element of our growth strategy is the Boyd Water Pipeline, designed to ensure that our beloved community has the necessary utilities for future expansion.
  • Catalyst Entertainment District: This City-owned entertainment district is a concept that will feature an arena, ice center, hotel, and an indoor waterpark. While the project is currently paused as we seek innovative financing options.

In September 2026, a district court ruled that the February 2026 ballot measure (Ballot Issue 1A) could not legally repeal the zoning approval Ordinance No. 30, 2025. The ordinance remains in effect.

The restoration of zoning did not restore Catalyst's financing. Catalyst's original funding plan was disrupted after the February vote, and the City has paused the project. No final decisions have been made about the Catalyst project.

Where Things Stand Today

  • Zoning: The PUD ordinance remains effective, ensuring the City can continue our plans for growth. The ordinance remains effective, and we can reapply for zoning if needed. You can read more about the ruling on our website.
  • Cascadia: Water Valley Company, the property owner, may continue development.
  • Catalyst: Paused while the City evaluates funding options and looks for a financial partner.
  • Oversight Committee: This group has completed its meetings, where it recommended pausing the Catalyst project while we look for a financial partner.
  • Weld County: Declined to become a partner on the Catalyst project in July 2026.
  • Ballot Measure 2F: A proposed 0.6% sales and use tax on the Nov. 3, 2026 ballot lists Catalyst among the projects it would fund. Learn more about 2F.
  • Existing obligations: The City is committed to repaying the Certificates of Participation (COPs), which funded early design and infrastructure work for the project, which is essential for moving forward. These must be repaid whether or not the Catalyst project moves forward.

Follow the Process

We will continue to update this page and our social media channels with news, including financing plans and partners. Past committee meetings, recordings, and materials are available in the Weekly Committee Recaps and the West Greeley Oversight document library.

Stay Informed

This is an active process, and this page will be updated as decisions are made. To understand how we got here, including past decisions, studies and materials, visit the Project History page.

Page Last Updated on October 8, 2026.

The West Greeley Project is an exciting long-term initiative aimed at planning for the future growth and development of Greeley’s western area! This project is all about fostering coordinated development, enhancing infrastructure, and encouraging economic investment within the city’s expanding western growth boundary.

Currently, several vibrant projects are underway on the west side of Greeley, each contributing to the area’s promising transformation:

  • Residential and Mixed-Use Neighborhoods:
    • One of the developments is Cascadia, a privately-owned residential and commercial community brought to life by the Water Valley Company. This project is set to move forward, creating a lively neighborhood for residents and visitors alike.
    • Additionally, we have other residential developments in the works, such as Delantero, Tri Pointe, and Poudre Heights, each poised to add unique living spaces to our community.Strategic Planning in Motion: The Vision for West Greeley Map
  • Community Infrastructure and Utilities: A key element of our growth strategy is the Boyd Water Pipeline, designed to ensure that our beloved community has the necessary utilities for future expansion.
  • Catalyst Entertainment District: This City-owned entertainment district is a concept that will feature an arena, ice center, hotel, and an indoor waterpark. While the project is currently paused as we seek innovative financing options.

In September 2026, a district court ruled that the February 2026 ballot measure (Ballot Issue 1A) could not legally repeal the zoning approval Ordinance No. 30, 2025. The ordinance remains in effect.

The restoration of zoning did not restore Catalyst's financing. Catalyst's original funding plan was disrupted after the February vote, and the City has paused the project. No final decisions have been made about the Catalyst project.

Where Things Stand Today

  • Zoning: The PUD ordinance remains effective, ensuring the City can continue our plans for growth. The ordinance remains effective, and we can reapply for zoning if needed. You can read more about the ruling on our website.
  • Cascadia: Water Valley Company, the property owner, may continue development.
  • Catalyst: Paused while the City evaluates funding options and looks for a financial partner.
  • Oversight Committee: This group has completed its meetings, where it recommended pausing the Catalyst project while we look for a financial partner.
  • Weld County: Declined to become a partner on the Catalyst project in July 2026.
  • Ballot Measure 2F: A proposed 0.6% sales and use tax on the Nov. 3, 2026 ballot lists Catalyst among the projects it would fund. Learn more about 2F.
  • Existing obligations: The City is committed to repaying the Certificates of Participation (COPs), which funded early design and infrastructure work for the project, which is essential for moving forward. These must be repaid whether or not the Catalyst project moves forward.

Follow the Process

We will continue to update this page and our social media channels with news, including financing plans and partners. Past committee meetings, recordings, and materials are available in the Weekly Committee Recaps and the West Greeley Oversight document library.

Stay Informed

This is an active process, and this page will be updated as decisions are made. To understand how we got here, including past decisions, studies and materials, visit the Project History page.
  • Boyd Water Pipeline Work at the Catalyst Site

    Share Boyd Water Pipeline Work at the Catalyst Site on Facebook Share Boyd Water Pipeline Work at the Catalyst Site on X (formerly Twitter) Share Boyd Water Pipeline Work at the Catalyst Site on Linkedin Email Boyd Water Pipeline Work at the Catalyst Site link
    Residents may see crews working near the Catalyst site through mid-October. This activity is paPhotos of Construction of the Boyd water pipelinert of the Boyd Water Transmission Line Relocation project and does not indicate a new phase of Catalyst construction.

    Crews are completing the final connection for two major water pipelines in the area. This project relocates the pipelines to support future development in west Greeley, replaces older pipeline sections with newer materials, and adds updated safety and operational features.

    The City is working to minimize construction impacts and maintain reliable water service throughout the project.


    Residents may see crews working near the Catalyst site through mid-October. This activity is paPhotos of Construction of the Boyd water pipelinert of the Boyd Water Transmission Line Relocation project and does not indicate a new phase of Catalyst construction.

    Crews are completing the final connection for two major water pipelines in the area. This project relocates the pipelines to support future development in west Greeley, replaces older pipeline sections with newer materials, and adds updated safety and operational features.

    The City is working to minimize construction impacts and maintain reliable water service throughout the project.


  • How COP Funds are Used in the Pre-Development Phase of West Greeley

    Share How COP Funds are Used in the Pre-Development Phase of West Greeley on Facebook Share How COP Funds are Used in the Pre-Development Phase of West Greeley on X (formerly Twitter) Share How COP Funds are Used in the Pre-Development Phase of West Greeley on Linkedin Email How COP Funds are Used in the Pre-Development Phase of West Greeley link

    The city is sharing a clear breakdown of how Certificates of Participation (COP) funds are anticipated to be used during the pre-development phase. In short, the largest share is expected to support design/engineering and site readiness work, including critical infrastructure like the Boyd waterline relocation and grading.

    Total anticipated COP-funded spending shown in the chart: $100.6 million. Where the funding is anticipated to go:

    • Design & Engineering at $46.7M: This includes architectural/engineering design for major components (arena, hotel, waterpark, civil and site work), plus project management and preconstruction oversight.
    • Site Work at $24.1M: Planned for site readiness items such as Boyd waterline relocation, overlot grading, erosion control, site access, and related field oversight.
    • Cost of issuance/interest carry at $10.9M: Financing-related costs, including issuance fees and capitalized interest.
    • Other project engineers/consultants at $5.7M: Project-specific support for engineering/management tied to design, entitlements, and preconstruction services.
    • City land costs at $5.2M: Costs associated with City land acquisition.
    • Additional City and project support costs combined at $7.8M: Includes City owner’s representatives ($3.5M), developer fee ($2.9M), City legal costs ($0.9M), and other City project costs ($0.5M).

    Why this Matters
    This breakdown highlights the essential preliminary work required to prepare for the next steps of the project. It outlines the practical tasks needed early on, as agreed under contract, including planning, design, engineering, and site and infrastructure preparation. These crucial infrastructure and planning phases are vital for the west side of Greeley as the city continues to grow and focuses on intentional development for the future. This groundwork allows the city to make informed decisions and be ready for the upcoming steps.

    The city is sharing a clear breakdown of how Certificates of Participation (COP) funds are anticipated to be used during the pre-development phase. In short, the largest share is expected to support design/engineering and site readiness work, including critical infrastructure like the Boyd waterline relocation and grading.

    Total anticipated COP-funded spending shown in the chart: $100.6 million. Where the funding is anticipated to go:

    • Design & Engineering at $46.7M: This includes architectural/engineering design for major components (arena, hotel, waterpark, civil and site work), plus project management and preconstruction oversight.
    • Site Work at $24.1M: Planned for site readiness items such as Boyd waterline relocation, overlot grading, erosion control, site access, and related field oversight.
    • Cost of issuance/interest carry at $10.9M: Financing-related costs, including issuance fees and capitalized interest.
    • Other project engineers/consultants at $5.7M: Project-specific support for engineering/management tied to design, entitlements, and preconstruction services.
    • City land costs at $5.2M: Costs associated with City land acquisition.
    • Additional City and project support costs combined at $7.8M: Includes City owner’s representatives ($3.5M), developer fee ($2.9M), City legal costs ($0.9M), and other City project costs ($0.5M).

    Why this Matters
    This breakdown highlights the essential preliminary work required to prepare for the next steps of the project. It outlines the practical tasks needed early on, as agreed under contract, including planning, design, engineering, and site and infrastructure preparation. These crucial infrastructure and planning phases are vital for the west side of Greeley as the city continues to grow and focuses on intentional development for the future. This groundwork allows the city to make informed decisions and be ready for the upcoming steps.

  • Overview of the Citizen Oversight Committee's Review

    Share Overview of the Citizen Oversight Committee's Review on Facebook Share Overview of the Citizen Oversight Committee's Review on X (formerly Twitter) Share Overview of the Citizen Oversight Committee's Review on Linkedin Email Overview of the Citizen Oversight Committee's Review link

    In spring 2026, the City of Greeley formed the West Greeley Citizen Oversight Committee to promote transparency and involve the community after the February 2026 referendum. The committee consisted of nine Greeley residents with different opinions: three who voted for the referendum, three who voted against it, and three who were unsure.

    West Greeley Citizen Oversight Committee Summary

    What the Committee Did
    From May to June 2026, the committee met every week for six weeks. Members reviewed information on the project, its costs, and design plans. They asked questions and considered different options for moving forward.

    Key Takeaways the Committee

    In spring 2026, the City of Greeley formed the West Greeley Citizen Oversight Committee to promote transparency and involve the community after the February 2026 referendum. The committee consisted of nine Greeley residents with different opinions: three who voted for the referendum, three who voted against it, and three who were unsure.

    West Greeley Citizen Oversight Committee Summary

    What the Committee Did
    From May to June 2026, the committee met every week for six weeks. Members reviewed information on the project, its costs, and design plans. They asked questions and considered different options for moving forward.

    Key Takeaways the Committee Considered

    As shared in the project overview brochure, the committee’s work took place in the context of:

    • The community’s direction from the February 2026 referendum, which the City interpreted as a signal to slow down, find the right financing approach, and bring residents into the process.
    • The reality that nearly $100 million had already been committed to feasibility studies, engineering, infrastructure development, and planning—meaning that walking away without a path forward could create pressure on existing City funds.

    The Committee’s Recommendation to Council
    At the June 9, 2026, City Council Work Session, the committee presented its first formal recommendation. The committee recommended that the City continue exploring a financial partner to help secure more favorable interest rates and recommended pausing the committee’s work until additional information becomes available.

    A brochure summarizing the committee’s work is available on the project's official document repository page.

  • City Provides Update on Cascadia, Catalyst Following Court Ruling on Ordinance No. 30

    Share City Provides Update on Cascadia, Catalyst Following Court Ruling on Ordinance No. 30 on Facebook Share City Provides Update on Cascadia, Catalyst Following Court Ruling on Ordinance No. 30 on X (formerly Twitter) Share City Provides Update on Cascadia, Catalyst Following Court Ruling on Ordinance No. 30 on Linkedin Email City Provides Update on Cascadia, Catalyst Following Court Ruling on Ordinance No. 30 link
    A 19th Judicial District court has ruled that the February 2026 special election measure seeking to repeal Ordinance No. 30 was unconstitutional, meaning the ordinance remains in effect. The City is sharing what this means for two West Greeley development projects:
    • Cascadia, a privately owned project developed by Water Valley Company, can continue moving forward.
    • Catalyst, the City-owned entertainment district project, remains paused while the City evaluates funding options.

    Read the full update for details on the court's reasoning and next steps.

    A 19th Judicial District court has ruled that the February 2026 special election measure seeking to repeal Ordinance No. 30 was unconstitutional, meaning the ordinance remains in effect. The City is sharing what this means for two West Greeley development projects:
    • Cascadia, a privately owned project developed by Water Valley Company, can continue moving forward.
    • Catalyst, the City-owned entertainment district project, remains paused while the City evaluates funding options.

    Read the full update for details on the court's reasoning and next steps.

  • August 13 Recap of the West Greeley Oversight Committee

    Share August 13 Recap of the West Greeley Oversight Committee on Facebook Share August 13 Recap of the West Greeley Oversight Committee on X (formerly Twitter) Share August 13 Recap of the West Greeley Oversight Committee on Linkedin Email August 13 Recap of the West Greeley Oversight Committee link

    Last week, August 13, the West Greeley Citizen Oversight Committee held its final scheduled meeting. The committee reviewed the project’s status, discussed options for moving forward and shared perspectives on potential paths to financing the project moving forward.

    Committee members discussed the project’s history, including work completed to date and the need to identify a workable path forward. The conversation reflected broad support for continuing to explore financing options to move the project ahead, while also recognizing that committee members held differing views on how that should happen and what approach would be most realistic and beneficial to the City of Greeley.

    The meeting also surfaced continued interest in clear, high-level information about project costs, timelines and what has happened to date. Those topics will remain important as the City considers next steps and future communication with the community.

    The committee’s discussion and input will be shared with City Council as it continues to consider the project’s path forward, including potential financing options.

    Watch the meeting recording on the City's Meeting Portal.


    Last week, August 13, the West Greeley Citizen Oversight Committee held its final scheduled meeting. The committee reviewed the project’s status, discussed options for moving forward and shared perspectives on potential paths to financing the project moving forward.

    Committee members discussed the project’s history, including work completed to date and the need to identify a workable path forward. The conversation reflected broad support for continuing to explore financing options to move the project ahead, while also recognizing that committee members held differing views on how that should happen and what approach would be most realistic and beneficial to the City of Greeley.

    The meeting also surfaced continued interest in clear, high-level information about project costs, timelines and what has happened to date. Those topics will remain important as the City considers next steps and future communication with the community.

    The committee’s discussion and input will be shared with City Council as it continues to consider the project’s path forward, including potential financing options.

    Watch the meeting recording on the City's Meeting Portal.


  • Weld County Declines to Partner with the City of Greeley on the Catalyst Project

    Share Weld County Declines to Partner with the City of Greeley on the Catalyst Project on Facebook Share Weld County Declines to Partner with the City of Greeley on the Catalyst Project on X (formerly Twitter) Share Weld County Declines to Partner with the City of Greeley on the Catalyst Project on Linkedin Email Weld County Declines to Partner with the City of Greeley on the Catalyst Project link

    The City of Greeley met with the Weld County Board of County Commissioners on July 20, 2026, to ask for help regarding the Catalyst Project, but the County Board turned down the request in a letter and has declined to become a partner in the funding for this project.

    The County Board affirmed its commitment to providing essential county services, including roads, public health, law enforcement, and more.

    The City of Greeley will continue to seek a financial partner, as recommended by the West Greeley Citizen Oversight Committee, for the Catalyst Project and to review other

    The City of Greeley met with the Weld County Board of County Commissioners on July 20, 2026, to ask for help regarding the Catalyst Project, but the County Board turned down the request in a letter and has declined to become a partner in the funding for this project.

    The County Board affirmed its commitment to providing essential county services, including roads, public health, law enforcement, and more.

    The City of Greeley will continue to seek a financial partner, as recommended by the West Greeley Citizen Oversight Committee, for the Catalyst Project and to review other alternatives. Updates will be shared by the city as they become available.

    View the presentation from the July 20 public meeting.

  • Joint City-County Meeting on West Greeley Project, July 20, 2026

    Share Joint City-County Meeting on West Greeley Project, July 20, 2026 on Facebook Share Joint City-County Meeting on West Greeley Project, July 20, 2026 on X (formerly Twitter) Share Joint City-County Meeting on West Greeley Project, July 20, 2026 on Linkedin Email Joint City-County Meeting on West Greeley Project, July 20, 2026 link

    The Greeley City Council and the Weld County Board of Commissioners held a joint public meeting on Monday, July 20, at 11:00 a.m. This meeting was in response to the recommendation from the West Greeley Citizens’ Oversight Committee (WGCOC) to seek a new financial partner for the West Greeley project. The WGCOC is a nine-member committee of citizens who represent a wide range of viewpoints on the proposed development in West Greeley that provides guidance to City Council members.

    During the meeting, city officials presented a high-level overview of the West Greeley Project and discussed potential partnership opportunities between

    The Greeley City Council and the Weld County Board of Commissioners held a joint public meeting on Monday, July 20, at 11:00 a.m. This meeting was in response to the recommendation from the West Greeley Citizens’ Oversight Committee (WGCOC) to seek a new financial partner for the West Greeley project. The WGCOC is a nine-member committee of citizens who represent a wide range of viewpoints on the proposed development in West Greeley that provides guidance to City Council members.

    During the meeting, city officials presented a high-level overview of the West Greeley Project and discussed potential partnership opportunities between the City of Greeley and Weld County. The aim is to explore collaboration options that will benefit both entities and further the development of this project.

    Access the City of Greeley’s meeting presentation at the following link: https://greeleyco.portal.civicclerk.com/event/3657/files/agenda/9241.

    The city is seeking further discussions with county officials in the coming weeks to explore alignment and collaboration on the West Greeley Project.

  • GroundFloor Media Selected to Support West Greeley Citizen Oversight Committee

    Share GroundFloor Media Selected to Support West Greeley Citizen Oversight Committee on Facebook Share GroundFloor Media Selected to Support West Greeley Citizen Oversight Committee on X (formerly Twitter) Share GroundFloor Media Selected to Support West Greeley Citizen Oversight Committee on Linkedin Email GroundFloor Media Selected to Support West Greeley Citizen Oversight Committee link

    The City of Greeley selected GroundFloor Media to help with communication and community involvement for the West Greeley Citizen Oversight Committee. This partnership aims to keep residents updated about the West Greeley Project and help the City communicate large projects in the future.

    Hiring expert consultants is common for cities handling big projects like this. These consultants have special skills in public communication and community engagement. The city selected GroundFloor Media for its strong plans and proven success.

    "GroundFloor Media impressed us with their clear plan to help residents understand the West Greeley Project," said Bret Naber, deputy city manager

    The City of Greeley selected GroundFloor Media to help with communication and community involvement for the West Greeley Citizen Oversight Committee. This partnership aims to keep residents updated about the West Greeley Project and help the City communicate large projects in the future.

    Hiring expert consultants is common for cities handling big projects like this. These consultants have special skills in public communication and community engagement. The city selected GroundFloor Media for its strong plans and proven success.

    "GroundFloor Media impressed us with their clear plan to help residents understand the West Greeley Project," said Bret Naber, deputy city manager. "Their team knows how to explain complex topics in simple language and create opportunities for real community conversation."

    Why GroundFloor Media

    GroundFloor Media is a Colorado-based communications firm with over 24 years of experience. They have worked with many cities in Colorado, including Denver, Lakewood, Grand Junction, Black Hawk, and Castle Pines. Their team is good at:

    • Turning difficult information into easy-to-understand materials like infographics, timelines, and short videos.
    • Planning town hall meetings and community events that allow the public to share their thoughts.
    • Creating messages that are easy for everyone to understand.
    • Supporting oversight committees and city staff with reliable information.

    GroundFloor Media will help develop strategies, create content, train committee members, support town hall meetings, and provide regular updates to the City Council and residents.

    To learn more about GroundFloor Media, visit their website at https://groundfloormedia.com/.

    About the West Greeley Project

    The West Greeley Project is a proposed effort focused on intentional community development, economic growth, and long-term benefits for the community. The Oversight Committee will keep reviewing project details, financing, and community impacts. GroundFloor Media will help share accurate information and encourage open discussions as this important work continues.

  • City of Greeley Seeks a Communication Consultant to Support West Greeley Citizen Oversight Committee and Public Education Materials

    Share City of Greeley Seeks a Communication Consultant to Support West Greeley Citizen Oversight Committee and Public Education Materials on Facebook Share City of Greeley Seeks a Communication Consultant to Support West Greeley Citizen Oversight Committee and Public Education Materials on X (formerly Twitter) Share City of Greeley Seeks a Communication Consultant to Support West Greeley Citizen Oversight Committee and Public Education Materials on Linkedin Email City of Greeley Seeks a Communication Consultant to Support West Greeley Citizen Oversight Committee and Public Education Materials link

    Below is an official news release from the City of Greeley:

    City of Greeley Seeks a Communication Consultant to Support West Greeley Citizen Oversight Committee and Public Education Materials

    Short-term engagement will help ensure consistent, transparent communication and timely delivery of materials

    GREELEY, Colo. – The City of Greeley seeks a skilled communication consultant. This agency will support the West Greeley Citizen Oversight Committee and create educational materials. The consultant will also help the city give clear and accessible information to residents, as well as share feedback and recommendations.

    The city and the previous consultant mutually agreed to discontinue

    Below is an official news release from the City of Greeley:

    City of Greeley Seeks a Communication Consultant to Support West Greeley Citizen Oversight Committee and Public Education Materials

    Short-term engagement will help ensure consistent, transparent communication and timely delivery of materials

    GREELEY, Colo. – The City of Greeley seeks a skilled communication consultant. This agency will support the West Greeley Citizen Oversight Committee and create educational materials. The consultant will also help the city give clear and accessible information to residents, as well as share feedback and recommendations.

    The city and the previous consultant mutually agreed to discontinue the contract. The city is now moving forward with a search for a new consultant to continue communication support.

    The city plans to choose from consultants who already have master service-level agreements. These firms have been vetted through the city’s process. This allows work to begin quickly and ensures continuity for the public.

    The West Greeley Citizen Oversight Committee was established to support transparency and public engagement. The committee helps ensure informed decision-making as the city considers the next steps for the West Greeley project. The support of a new consultant will:

    • Share clear and regular updates about the committee’s work and key project updates.
    • Create educational materials to help residents understand the project and the information available.
    • Help make complex information easier to understand and present it in a way that is friendly for the public.

    The city hopes to engage a new consultant by the end of June. For updates on the West Greeley Project, https://speakupgreeley.com/west-greeley-project-update.

    ###


  • Oversight Committee Presents Findings and Recommendations to Council

    Share Oversight Committee Presents Findings and Recommendations to Council on Facebook Share Oversight Committee Presents Findings and Recommendations to Council on X (formerly Twitter) Share Oversight Committee Presents Findings and Recommendations to Council on Linkedin Email Oversight Committee Presents Findings and Recommendations to Council link

    At the June 9 Council Work Session, Greeley City Council received the first formal recommendation from the West Greeley Citizen Oversight Committee.

    After six weeks of reviewing project information, asking questions and evaluating potential paths forward, the committee recommended that the City continue exploring a financial partner that could help secure more favorable interest rates for the project. The committee also recommended pausing its work until additional information becomes available.

    Committee members requested updated project costs, economic development projections, and potential financing details before continuing discussions. If a financing partner is identified, the committee is expected to reconvene to review

    At the June 9 Council Work Session, Greeley City Council received the first formal recommendation from the West Greeley Citizen Oversight Committee.

    After six weeks of reviewing project information, asking questions and evaluating potential paths forward, the committee recommended that the City continue exploring a financial partner that could help secure more favorable interest rates for the project. The committee also recommended pausing its work until additional information becomes available.

    Committee members requested updated project costs, economic development projections, and potential financing details before continuing discussions. If a financing partner is identified, the committee is expected to reconvene to review the information and continue its evaluation of potential next steps.

    View the agenda, presentation, and meeting recording in the Key Dates section.